Platform Lift Factory Acceptance Checks
Before a bespoke platform lift leaves the factory, agree what to witness, record assembly and function checks, and assign any checks that depend on installation.
Structural discrepancies of 40–50 mm, when forming the lift pit, can affect pit depth, finished floor levels and stair geometry when installing a bespoke platform lift.
Early identification of double slabs or unexpectedly high structural floors helps prevent delays and unnecessary re-fabrication.
Sesame Access can adjust stair frames, riser heights, track lengths and pit trims without redesigning the lift mechanism.
In this case, raising the lower landing by one full riser is more efficient than modifying every tread individually.
Collaboration between contractor and lift engineer ensures the safest, most cost-effective solution for heritage and refurbishment projects.
Site-level discrepancies of 40–50 mm during installation can compromise pit depth requirements for a bespoke platform lift. This challenge commonly appears during refurbishment projects, especially when demolition reveals hidden structural slabs beneath assumed finishes. When the lower landing level sits higher than anticipated, the available pit depth reduces, and critical lift interfaces must be reconsidered.
This article explains, step by step, how Sesame Access assesses the issue, models the impact and recommends the most practical engineering solution. The content is based on a real technical meeting, showing how adjustments can be made even when the lift is already three-quarters through fabrication.
Unexpected level changes typically arise when removal of finishes reveals a secondary structural slab. The lift pit depth and landing interface are then no longer aligned with the original drawings. This affects:
Pit depth tolerance
Stair frame height
Riser consistency
Track and tread alignment
Pit trim position
A bespoke platform lift such as the Mayfair Stairlift requires precise step geometry. Even small variances can influence how the lifting table aligns with the lower and upper landings.
For further technical context, see:
Designing Bespoke Heritage Staircase Lifts → https://www.sesameaccess.com/knowledge-hub/designing-bespoke-heritage-staircase-lift
Bespoke Lift Pit Depth Solutions → https://www.sesameaccess.com/knowledge-hub/bespoke-lift-pit-depth-solutions
A minimum pit depth (in this case 662 mm) is essential for the lift to operate safely. If the structural slab sits 40–50 mm higher than expected, two primary routes can be considered.
This may involve scabbling, breaking out concrete or recasting a section of the slab to restore the original design level. While this preserves the lift assembly, it can add noise, disruption and programme impact.
Sesame can usually adapt the architectural components during build if necessary. Typical adjustments include:
Cutting and re-welding the stair frame
Compressing each riser by several millimetres if tolerances allow
Shortening lift tracks
Re-positioning fixing brackets
Modifying or replacing pit trims
Adjusting tread geometry
Products like the Jubilee Disabled Access Lift and Wembley Stair Lift use similar step-integration techniques, and these modifications are routine for the engineering team.
Often, yes. In the meeting, the contractor queried whether raising the lower landing by one full riser (for example, ~158 mm) would be simpler than fine-tuning every step.
Removing a riser can:
Avoid replacement of multiple stainless-steel treads
Reduce welding work
Simplify adjustments to the stair frame
Reduce the total engineering hours
Produce a cleaner final finish
The lift tracks may project slightly until cladding is applied, but this is acceptable and does not reduce long-term performance.
Because each lift is bespoke, components are designed, cut and part-assembled early in production. However, Sesame can still carry out:
Frame cutting and re-welding
Track shortening
Tread adjustments
Riser compression
Re-packing the lift base
Pit trim repositioning
This typically requires around 1-2 weeks of engineering time depending on the solution chosen.
The engineering team needs to know:
The exact new lower landing level
The minimum rise adjustment achievable through scabbling
Whether a full riser removal is acceptable architecturally
Any constraints affecting the upper landing interface
Restrictions from adjacent finishes or shopfronts
Providing these values enables Sesame to quote the most cost-efficient option and avoid unnecessary manufacturing work.
Only if the reduction falls within the very small 25mm tolerance allowed. Otherwise, stair and frame adjustments are essential.
No. Sesame recalculates all rise heights to maintain consistency and compliance.
No. The mechanism stays the same; only the staircase structure adjusts.
Yes. The engineering team regularly performs controlled last-minute modifications.
Yes, and it can be the most efficient solution when the structural discrepancy is large.
What is the fastest way to resolve a 40–50 mm site-level error?
In many cases, removing a riser and raising the lower landing is more efficient than adjusting every tread.
Do track or pit trim components need replacing?
Sometimes. Track sections may need shortening, and pit trims may need replacing depending on the adjustment route.
Can Sesame advise before major site works begin?
Yes. Early communication prevents unnecessary demolition or re-fabrication.
Does modifying the stair frame delay installation?
Usually about a week of engineering time.
Are bespoke lifts flexible enough for heritage buildings?
Yes. Solutions used on products like the Mayfair Stairlift and Jubilee Disabled Access Lift are designed exactly for these conditions.
For support with pit depth changes, riser discrepancies or bespoke lift integration, book a meeting with a Sesame Project Manager:
https://www.sesameaccess.com/book-a-meeting
Udostępnij
Before a bespoke platform lift leaves the factory, agree what to witness, record assembly and function checks, and assign any checks that depend on installation.
A practical guide to deciding when bespoke platform lifts can share a bracket, with checks for movement, tolerances, service access and drawing revisions.
A planning guide for New York City platform lifts covering DOB filings, installer licensing, first inspection and the roles to agree before procurement.