Lift Installation

With over 20 years of experience, Sesame Access has developed in conjunction with our partners companies the following procedure to ensure a two week lift installation and prompt handover. Deviations from the following steps may result in delays to the install and practical completion dates.

1) The Lift Pit

  • Pre-install inspection of pit must take place minimum of 1 week before install
  • Sesame cannot inspect the pit until it is finished with all gridlines and datums
  • The pit must be clean, and clear of all debris and other trades
  • Delivery and installation details will be covered
  • See "Pre-Install Checklist" below

Pit Drawing, Click to Enlarge

2) Lift Delivery and Install

  • The trim/lining of the pit arrives first, and is fixed and levelled
  • The Sesame lift will be delivered via Hiab and if possible, lowered directly into the pit
  • If the Hiab cannot lower into the pit, a gantry crane will be used to traverse lift into position
  • Once in place, Sesame engineers will install the lift and get it up and running
  • See below "Pit-Trim Sign Off", "Standard Install RAMS" and "Data Sheets"

Lift transporting by Hiab

3) Cladding and Commissioning

  • The cladding must be cut to size, and permanent power must be on site to begin the second week
  • Sesame will supervise the cladding of the lift, to ensure all requirements and standards are met
  • The final installation steps, including commissioning and testing

Cladding Samples - Click to Enlarge

4) Handover

  • All handover and testing documents are issued from the Sesame head office
  • The client must receive training on correct and safe lift operation
  • All Sesame lifts come with a 1 year warranty, and one standard service after 6-month. Click here for service details
Retracting Stair Red Lion
The Finished Product

Downloads

PDF 387.44KB

PDF 681.69KB

PDF 1.61MB