Lift Installation
With over 20 years of experience, Sesame Access has developed in conjunction with our partners companies the following procedure to ensure a two week lift installation and prompt handover. Deviations from the following steps may result in delays to the install and practical completion dates.
1) The Lift Pit
- Pre-install inspection of pit must take place minimum of 1 week before install
- Sesame cannot inspect the pit until it is finished with all gridlines and datums
- The pit must be clean, and clear of all debris and other trades
- Delivery and installation details will be covered
- See "Pre-Install Checklist" below
Pit Drawing, Click to Enlarge
2) Lift Delivery and Install
- The trim/lining of the pit arrives first, and is fixed and levelled
- The Sesame lift will be delivered via Hiab and if possible, lowered directly into the pit
- If the Hiab cannot lower into the pit, a gantry crane will be used to traverse lift into position
- Once in place, Sesame engineers will install the lift and get it up and running
- See below "Pit-Trim Sign Off", "Standard Install RAMS" and "Data Sheets"
Lift transporting by Hiab
3) Cladding and Commissioning
- The cladding must be cut to size, and permanent power must be on site to begin the second week
- Sesame will supervise the cladding of the lift, to ensure all requirements and standards are met
- The final installation steps, including commissioning and testing
Cladding Samples - Click to Enlarge
4) Handover
- All handover and testing documents are issued from the Sesame head office
- The client must receive training on correct and safe lift operation
- All Sesame lifts come with a 1 year warranty, and one standard service after 6-month. Click here for service details
Downloads
PDF 387.44KB
PDF 681.69KB
PDF 1.61MB